Timeline
This page shows a timeline of expected works and activity planned by contractor, Neilcott.
The City of London and project team are committed to continuing regular Community Steering Group meetings and Community Update meetings thoughout the works.
-
Spring 2024
Investigation works on the podium (lifting slabs) -
18 March - April 2024
Investigation works in Gravel Lane shop units -
Thursday 4 April 2024
Drilling Work
9am-10.30am
Investigative drilling work on basement car park ramp. Some noise during work but ramp will remain open.
-
22- 25 April 2024
Podium Investigation Works
Monday 22nd – Open up the six areas
Tuesday 23rd – Inspection of findings
Wednesday 24th – Close up areas
Thursday 25th - Clean-up day
-
26 April 2024
Resident workshops on planting and accessible play, Artizan Street Library at 10.30am and 12pm -
Monday 15 July 2024
Follow-up workshop for planting and podium maintenance held at Artizan Street Library
-
Monday 22 July 2024
Asbestos removal work continuing in units 8-18 Gravel Lane for 4 weeks
-
Wednesday 31 July 2024
Ball court closed on 31 July-1 August for maintenance work
-
19 August 2024
Plaster removal in Gravel Lane units
-
2 September 2024
Opening up works between units in Gravel Lane
-
17 September 2024
CSG meeting
Residents Association Meeting - Neilcott to attend and give an update on the construction programme.
-
28 October 2024
Demolition of stairs (noisy works). Delayed from 14 October.
-
6 January 2025
Estimated start date for major internal works
-
Spring 2026
Estimated completion